Housing Water Main Repair, Beale AFB, CA

 

  • Exceptional Past Performance Evaluation
  • Sustainment, Restoration and Modernization (SRM) Project

 

 

Design-Build of repair of water mains that service base housing on Beale AFB. This project replaced approximately 6,032 linear feet of water main by pulling waterline through existing pipe.

 

Work also included gate valves, blow-off valves, air-release valves, and fittings. Additional work items included abandonment-in-place of existing water facilities, connection of new water lines to the existing distribution system, restoration of concrete, asphalt, and landscaping and updated as-built information documenting the location of new and existing facilities.